Core Improvements Swarm
Summary and Goal(s)
Status Core Improvements swarm's goal is the preparation of Status Mobile Client to be released publicly (AppStore/GP release tracks).
A few key areas that we need to focus on:
-
all the critical security and privacy issues are resolved (including audit);
- a security and privacy document is delivered (it lists guarantees we make around security and privacy; as well as ways we are falling short)
-
all the critical tech debt issues are resolved;
-
key UX problems are solved in two areas:
- adoption issues;
- retention issues.
The work includes releasing internal "dogfood" builds as well as betas in preparation to the public release.
Additional contributors
- Andrea MP
- Andrei M (Design)
- Serhy/Anna/Nastya(QA)
- Rachel/Hester (PO)
Communication
(required)
status channel (same as Core Team)
: #status-core
sync frequency
: Weekly Sync Mondays, 10:00 CET (the regular "Core Team" standup)
meeting notes
: this running doc on notes.status.im
Research
Meta - Done
Meta (what this team will be doing?)
Backlog is created
3. Improve Security using native views - Done
PoC is created for using native views
Specification
2. "Save Password" on Android - Done
Epic: https://github.com/status-im/status-react/issues/5793
Implementation
Done
0. Meta
- Timeline - EOQ2 2019, continuous process. Each backlog item discovered by research will have it's own deadline.
Setup a regular meetings with the stakeholders to adjust the backlog.
document progress
- keep the backlog and the state up to date with this
document.
Projects from should be put in the correct state to see the progress, etc.
1. Message Reliability Improvements
- Timeline - January, 31
document progress
: https://www.pivotaltracker.com/epic/show/4178343
2. "Save Password" on Android
- Timeline - January, 21th
document progress
: https://www.pivotaltracker.com/epic/show/4179882
3. Slow sign-in - DONE
4. Dependency audit for reproducible builds
- Timeline - January, 25
document progress
: https://www.pivotaltracker.com/epic/show/4182830
5. Fix critical issues with traffic consumption
- Timeline - January, 31
document progress
: https://www.pivotaltracker.com/epic/show/4182828
Maintenance
1. Battery usage
2. Application performance profiling
3. Mobile Releases
- Mobile release guide
- Mobile release notes
- Upgrade policy
- User’s data. User should be able to successfully upgrade preserving all his/her data from 0.9.19 to any beta release.
- Messaging/Transactions. User should be able to successfully interact (make transactions, chat, etc) with users that have 0.9.20 or later release.
Backlog
See Pivotal Tracker: https://www.pivotaltracker.com/n/projects/2232205
Copyright