# Release Process Guide
|
|
|
|
This guide is meant to explain the flow and rules of the release process, i.e. the period when we cut a release branch off the master branch in anticipation of releasing it to users. Release Candidates (RC) are provided to test the Release.
|
|
|
|
## Before the release process
|
|
|
|
1. Close all the must have issues of the milestone.
|
|
1. The release process **must never** be started if must have issues still exist.
|
|
2. Either postpone the release or de-scope the must have issues.
|
|
2. Disable feature flags of any features that didn't get completed.
|
|
1. See the [Cross-Team Epic Delivery Workflow](epic-delivery-workflow.md) document for the definition of a completed feature.
|
|
3. Define a priority matrix prior to the testing day.
|
|
1. This matrix should explain what constitutes a Must have, Should have and Could have bug for the release.
|
|
2. Keep in mind that only the must have issues **should** be worked on during the release process, all others **should** be moved to the next milestone.
|
|
4. One or more testing days **should** be done by the entire Status team to find any regressions before cutting.
|
|
1. The Status team **should** split in testing groups to help test features.
|
|
2. Testing groups **should** contain people from different teams to spread the knowledge.
|
|
3. Testing days **should** happen on days where most of the team is available.
|
|
4. Testing days **must** use a list of current features to test.
|
|
5. The list **should** include a column listing issues found and by whom.
|
|
6. The list **should** include an indicator whether that feature is covered by end-to-end (e2e) test and/or functional tests.
|
|
7. The list **should** contain a section documenting which features were recently **added** or **refactored**.
|
|
8. The recently added or refactored features **should** be the most tested.
|
|
9. Features on the list **can** be tested by multiple testing groups.
|
|
10. Testing days **can** happen during the release process too.
|
|
|
|
## During the release process
|
|
|
|
1. A release branch **must** be created at the start of the Release Process for the [Status App](https://github.com/status-im/status-app)'s master branch and [status-go](https://github.com/status-im/status-go)'s develop branch
|
|
1. The format for the status-app branch is `release/MAJOR.MINOR.x`, eg. `release/2.36.x`
|
|
2. The format for the status-go branch is automatically done using the Release script. Ask a status-go maintainer to create it.
|
|
3. The status-app release branch **must** always point to the status-go release branch.
|
|
2. The first RC of the release branch **should** be sent to the Apple App Store immediately
|
|
1. This ensures that any question from the Apple review team can be answered and addressed as soon as possible
|
|
2. Once the release is ready, the final build will be sent to the App Store and **should** pass easily
|
|
3. All remaining issues from the milestone should be moved to the next milestone.
|
|
1. Issues needing to be fixed on the RC will be added to the current milestone.
|
|
|
|
4. Only bug fixes **must** be provided to the release branch.
|
|
|
|
5. Moreover, only **critical** bug fixes **should** be added to the current milestone and committed to the release branch.
|
|
1. Critical bugs are issues that affect:
|
|
1. security
|
|
2. potential data or funds loss
|
|
3. crashes
|
|
4. full regressions
|
|
|
|
6. Regressions **should** be mentioned to the QA team so that they can plan and implement e2e tests to prevent further regressions of this sort (to be implemented on master).
|
|
1. Use the `needs-autotests` label on the issue to flag it.
|
|
|
|
7. Code coverage does **not** need to be met on the release branch.
|
|
|
|
8. Features **must not** be allowed to be added to the release branch under any circumstances.
|
|
|
|
9. Fixes for issues identified during the RC phase **must** be worked on and committed on the release branch **first**.
|
|
|
|
10. A new RC build **can** be triggered every day, if there are new fixes in the release branch.
|
|
|
|
11. Releases and RCs **must** have unique semantic numbers in the `VERSION` file and `tag`.
|
|
1. Release format: `2.36.0`
|
|
2. RC format: `2.36.0-rc.1`
|
|
|
|
12. The commit updating the `VERSION` file **must** have a `tag` matching the same version number on it.
|
|
|
|
13. The release branch **must** be rebased on top of the master branch each time a new RC is cut
|
|
1. This ensures that the master branch stays up to date with the release branch
|
|
2. It also lowers the amount of effort needed by devs, as no one needs to cherry-pick
|
|
|
|
|
|
## After the release process
|
|
|
|
1. A release is considered done once the builds are published to the stores and on Github, plus the release branch is fully rebased on top of master.
|
|
2. A new tag **must** be created on the master branch's latest commit with the new version and the `-dev` suffix. eg: `2.39.0-dev` if `2.38.0` was just published.
|
|
3. The Status community's control node **should** be updated to the latest version.
|
|
4. The Status-Discord bridge **should** be updated to the latest version.
|
|
5. Blog posts and News Feed articles **should** be posted.
|
|
|
|
## Frequently asked questions
|
|
|
|
### When is a release ready to be cut?
|
|
|
|
A release is considered ready to be cut when all **Key** features are **Done** and when all the must have issues are closed.
|
|
|
|
A **Key** feature is a feature identified on the [Roadmap](https://github.com/status-im/status-app/blob/master/docs/roadmap.md) as the most important features for that release.
|
|
|
|
A feature is considered **Done** when all issues of its Epic are closed. An Epic **must** include a testing issue, where one of the dev who worked on the issue meets with one of the designers and/or the Product Manager to demo the issue. Designers and/or the PM **should** open any issue they find on the new feature. Refer to the [Epic Delivery Workflow guide](/docs/internal/epic-delivery-workflow.md) for the full rundown.
|
|
|
|
#### What happens to the other features not ready at the time of the release cut?
|
|
|
|
The remaining features listed on the [Roadmap](https://github.com/status-im/status-app/blob/master/docs/roadmap.md) on the same milestone, but that were not identified as **key**, will simply be pushed to the next milestone.
|
|
|
|
All new features **must** implement a **feature flag**. Therefore, unfinished features **must not** affect negatively the master and release branches.
|
|
|
|
### Why commit to the release branch first and not master?
|
|
|
|
1. It is faster for the release.
|
|
2. Less possibilities of conflicts on the release branch.
|
|
3. Cherry-picked commits are often **not** tested. That is acceptable on master, but **unacceptable** on the release branch.
|
|
4. Issues do **not** close as completed when merged on the release branch. Therefore, it is easy to spot that the commit needs to be cherry-picked to master.
|
|
|