# Waku Project Management
|
||
|
||
Tracks/coordinate effort/tasks that targets Waku as a product across implementations (production readiness, scalability, etc).
|
||
|
||
## Teams
|
||
|
||
The Waku Team is currently split in the following subteams:
|
||
|
||
- Waku Research
|
||
- Waku Development (nwaku, js-waku, go-waku)
|
||
- Waku Eco Dev (DevRel, Docs)
|
||
|
||
## Work Tracking and Reporting Guidelines
|
||
|
||
### Requirements
|
||
|
||
The current reporting requirements are 2 folds:
|
||
|
||
#### 1. Weekly Reporting
|
||
|
||
Weekly reporting on work progress by milestones.
|
||
|
||
#### 2. Monthly Reporting
|
||
|
||
Monthly reporting is now handled by the Logos insight team.
|
||
|
||
### Terminology
|
||
|
||
| Name | Number of | Timeframe | Team Scope | Owner | Description |
|
||
|-----------------|-----------------------------------------|----------------------------------------|----------------------------------------------|-----------------------------|-----------------------------------------------------------------------------|
|
||
| (Key) Milestone | 1-3 per year | Set yearly-ish/as needed | Most subteams | Waku Lead | Key achievements for the Waku project, historical milestones. |
|
||
| Epic | Several per milestone | Set for a milestone, delivered monthly | Several subteams or external team (e.g. DST) | Team Members | Chunk of a _Milestone_ across all clients. |
|
||
| Task | Many per Epic | Set monthly-ish, delivered weekly | One subteam or individual | Team Member | May be one or several piece of work, client specific. |
|
||
|
||
### Epic Owner Responsibilities
|
||
|
||
Each epic should have an owner per affected subteam (research, js-waku, go-waku, nwaku).
|
||
|
||
The epic owner is responsible for breaking down the work in smaller issues in the related repo.
|
||
|
||
For research team, it is expected that most of the research work is done by the epic owner, which includes:
|
||
- Capturing problem statement
|
||
- Designing protocol/solution
|
||
- Implementing PoC in reference implementation
|
||
- Running tests/simulations to confirm behaviour (to be offloaded to test engineer once hired)
|
||
|
||
For development teams, it is expected that design/break down is done by epic owner.
|
||
But actual workcan be picked up by other team member.
|
||
Epic owner must:
|
||
|
||
- Understand the change and its implications,
|
||
- Liaise with researcher for any doubt or questions or design issues related to specific client/use case,
|
||
- Create issues (_Tasks_) to break down work in client repo, include an _acceptance criteria_ in each issue to ensure that the objective/end goal/behaviour is clearly described.
|
||
|
||
It is likely that the epic owner will do the core change or first change for a given epic.
|
||
However, subsequent/other changes may be picked up in parallel or sequentially by other team members.
|
||
|
||
Hence:
|
||
- dependencies must be clearly stated in _Task_ issue description
|
||
- Team members must assign _Task_ issues to themselves when work starts
|
||
- Team member must update issues to track progress
|
||
|
||
The program manager should ensure that epics are getting the right assignee in a timely fashion.
|
||
For example, when research work starts for a given epic, epic owners from development team should be assigned, so they know to participate in discussions.
|
||
Program manager should also ensure that issues are being created in a timely fashion,
|
||
an is encouraged to use client PM call as a forum to check epics to be assigned.
|
||
For example, when PoC is near completion then breaking down the work should be started.
|
||
|
||
### GitHub Usage
|
||
|
||
A _Milestone_:
|
||
- MUST have a matching GH issue in the https://github.com/waku-org/pm repo with `milestone` label assigned.
|
||
- MUST have a GH Milestone in https://github.com/waku-org/pm repo, to which relevant _Epics_ are added.
|
||
- SHOULD have a roadmap to delivery done at planning phase, the GH milestone is then used to track progress.
|
||
|
||
An _Epic_:
|
||
- MUST have a matching GH issue in the https://github.com/waku-org/pm with `epic` label assigned.
|
||
- MUST have a label with format `E:<epic name>` created across all relevant https://github.com/waku-org/ repos (see [labels.yml](./.github/labels.yml)).
|
||
- SHOULD be added to a GH Milestone.
|
||
- SHOULD have a `Planned Start` and `Due Date` set (these are GitHub projects fields you can find in the `Projects` section of the issue view sidebar).
|
||
- MAY list _Tasks_ present in other repos.
|
||
- MUST have one assignee **per subteam**, who represent the epic owner.
|
||
|
||
A _Task_:
|
||
- MAY be tracked as a todo item in a GH Issue (_Task_ or _Epic_),
|
||
- OR MAY be tracked as a single GH issue
|
||
- that MUST be labelled with related _Epic_ label (`E:...`),
|
||
- OR MAY be tracked as a GH Pull Request
|
||
- that MUST be labelled with related _Epic_ label (`E:...`),
|
||
- MUST have an _acceptance criteria_ and/or a list of _tasks_ (that can be other GH issues).
|
||
|
||
Finally, for _Tasks_ that do not belong to a given _Epic_ or _Milestone_:
|
||
- MUST have either labels:
|
||
- `bug`: This is a bug, likely reported by a user
|
||
- `enhancement`: This is an enhancement out of the scope of the technical roadmap, likely reported by a user
|
||
- Major enhancements should be carefully reviewed and prioritized.
|
||
- `documentation`: Documentation improvement or correction.
|
||
- `dependencies`: Upgrade dependencies in a timely manner to avoid time wasting when the dependency upgrade becomes critical.
|
||
|
||
|
||
Which means, in terms of _navigation_:
|
||
|
||
- Work for a Milestone is described in the related GitHub issue and tracked in the GitHub milestone.
|
||
- In the GitHub milestone, we have a list of _Epics_ to be achieved, the _Epics_ are being closed as the work is done across all clients.
|
||
- To look at remaining work for an _Epic_, one need to look at all issues/PRs (_Tasks_) with the corresponding _Epic_ label (`E:...`)
|
||
|
||
### Reporting
|
||
|
||
**Monthly**:
|
||
|
||
Handled by insight team
|
||
|
||
**Weekly**:
|
||
|
||
Report progress on each **active** _Epic_ or _Task_ per sub-team.
|
||
|
||
Every Friday, all team members must add their update in the appropriate discord thread *WITH LINKS* to the GitHub **issues** (not pull requests) they own and worked on over the past week and/or plan to work on next week.
|
||
|
||
If work is done on several *Tasks* related to the same *Epic*, team members are free to link the common parent *Epic* issue.
|
||
|
||
Please include an update for the following categories:
|
||
|
||
- achieved: what was achieved this week.
|
||
- next: what will be worked on next.
|
||
- blocked: blocking items, not required if no blockers exist.
|
||
|
||
On Mondays PM compiles the updates following sign-off from sub-team Leads and publishes to https://roadmap.logos.co.
|
||
|
||
### Process Flow
|
||
|
||
```md
|
||
Submit Updates (Everyone) - Friday
|
||
│
|
||
▼
|
||
Review/Signoff (Leads) - Monday
|
||
│
|
||
▼
|
||
Compile (PM) - Monday
|
||
│
|
||
▼
|
||
Publish (PM) - Tuesday
|
||
```
|
||
|
||
## Milestones
|
||
|
||
https://github.com/waku-org/pm/milestones
|