# Waku Project Management
|
|
|
|
*For tracking and project management processes please see* [PROCESS.md](./PROCESS.md)
|
|
|
|
## Weekly Reporting
|
|
|
|
Weekly reporting provides an insight on the progress by Milestones. Updates are published to https://roadmap.logos.co/tags/waku-updates.
|
|
|
|
- Updates are collected and submitted by the team leads.
|
|
- Add to the relevant pull request in the roadmap repository: https://github.com/logos-co/roadmap/pulls
|
|
- Provide updates for each Deliverable currently in-progress.
|
|
- Use the achieved, next, blockers format templated under each Deliverable.
|
|
- Indicate if there is a scope change or due date change.
|
|
- Indicate which team the update is for, e.g.:
|
|
```md
|
|
- achieved:
|
|
- [nwaku] Added testing for…
|
|
- [chat] Update libraries in…
|
|
```
|