Items to complete
All items below are to be completed by the owner of the given release.
-
Create release branch with major and minor only ( e.g. release/v0.X ) if it doesn't exist.
-
Assign release candidate tag to the release branch HEAD (e.g.
v0.X.0-rc.0,v0.X.0-rc.1, ...v0.X.0-rc.N). -
Generate and edit release notes in CHANGELOG.md.
-
Validation of release candidate
-
Automated testing
- Ensure all the unit tests (specifically logos-messaging-js tests) are green against the release candidate.
-
QA testing
- Ask QA to run their available tests against the release candidate.
-
Waku fleet testing
- Deploy the release candidate to
waku.testfleet.- Start the deployment job and wait for it to finish (Jenkins access required; ask the infra team if you don't have it).
- After completion, disable fleet so that daily CI does not override your release candidate.
- Verify at https://fleets.waku.org/ that the fleet is locked to the release candidate image.
- Confirm the container image exists on Harbor.
- Search Kibana logs from the previous month (since the last release was deployed) for possible crashes or errors in
waku.test.- Set time range to "Last 30 days" (or since last release).
- Most relevant search query:
(fleet: "waku.test" AND message: "SIGSEGV"),(fleet: "waku.test" AND message: "exception"),(fleet: "waku.test" AND message: "error"). - Document any crashes or errors found.
- Ask QA to perform tests against
waku.test, if any. Then, after that, review Kibana for possible issues or unexpected restart. - Enable the
waku.testfleet again to resume auto-deployment of the latestmastercommit.
- Deploy the release candidate to
-
Status testing
- Get QA approval to deploy a new version in
status.staging. - Deploy release candidate to
status.staging. - Perform sanity check and log results as comments in this issue.
- Connect 2 instances to
status.stagingfleet, one in relay mode, the other one in light client mode.- 1:1 Chats with each other.
- Send and receive messages in a community.
- Close one instance, send messages with second instance, reopen first instance and confirm messages sent while offline are retrieved from store.
- Perform checks based on end user impact
- Inform other (Waku and Status) CCs to point their instances to
status.stagingfor a few days. Ping Status colleagues on their Discord server or in the Status community (this is not a blocking point.) - Ask QA to perform sanity checks (as described above) and checks based on end user impact; specify the version being tested
- Ask QA or infra to run the automated Status e2e tests against
status.staging - Get other CCs' sign-off: they should comment on this PR, e.g., "Used the app for a week, no problem." If problems are reported, resolve them and create a new RC.
- Connect 2 instances to
- Get QA approval to deploy a new version in
-
-
Proceed with release
- Assign a final release tag (
v0.X.0) to the same commit that contains the validated release-candidate tag (e.g.git tag -as v0.X.0 -m "final release."). - Update logos-delivery-compose and logos-delivery-simulator according to the new release.
- Bump logos-delivery dependency in logos-delivery-rust-bindings and make sure all examples and tests work.
- Bump logos-delivery dependency in logos-delivery-go-bindings and make sure all tests work.
- Create GitHub release (https://github.com/logos-messaging/logos-delivery/releases).
- Submit a PR to merge the release branch back to
master. Make sure you use the option "Merge pull request (Create a merge commit)" to perform the merge. Ping repo admin if this option is not available. - Create a deployment issue with the recently created release.
- Assign a final release tag (