Using Pivotal Tracker
|
||
|
===
|
||
|
|
||
|
## Abstract
|
||
|
|
||
|
The Core Improvements swarm tracks its workflow in a Pivotal project. Although GitHub items can still be created to facilitate communication, the official way to track progress of a functionality/bug fix is in Pivotal.
|
||
|
|
||
|
[Project board link](https://www.pivotaltracker.com/n/projects/2232205)
|
||
|
|
||
|
## Creating Pivotal Stories
|
||
|
|
||
|
Fill in `Story Type`, `Requester`, `Owner` (if already assigned), and `Points` (if an estimate is available). Add a description and optionally group it using a label. As a rule of thumb, Pivotal stories should be grouped in epics for better high-level visibility. Although labels can be used to group stories, the prescribed way to do that is through epics.
|
||
|
|
||
|
You can add tasks under a Story for smaller items that don't warrant its own Story.
|
||
|
|
||
|
Do add the link to the Pull Request to the Story when one is available.
|
||
|
|
||
|
## Lifetime of a Pivotal story
|
||
|
|
||
|
The `State` field in the Pivotal story is used to track the progress of a Pivotal Story, and has the following interpretation:
|
||
|
|
||
|
| State | Meaning |
|
||
|
| ---------- | -------- |
|
||
|
| `Unstarted` | In backlog |
|
||
|
| `Started` | Developer has started work on story |
|
||
|
| `Finished` | Developer has finished work on story (Pull Request for story is in [REVIEW](https://github.com/status-im/status-react/projects/7#column-1843024) column in [Pipeline for QA](https://github.com/status-im/status-react/projects/7) board) |
|
||
|
| `Delivered` | Pull Request for story is in testing in [Pipeline for QA](https://github.com/status-im/status-react/projects/7) board) board |
|
||
|
| `Accepted` | PR has been merged |
|
||
|
| `Rejected` | PR has been aborted |
|
||
|
|
||
|
### Rules of thumb
|
||
|
|
||
|
- **Q:** _When to create a Pivotal story?_
|
||
|
**A:** Stories should be created whenever estimated work exceeds half a day, or when part of a bigger epic.
|
||
|
|
||
|
- **Q:** _What do points equate to?_
|
||
|
**A:** We've agreed to make 3 points equate roughly to 1 day of work. From there, we can extrapolate:
|
||
|
|
||
|
| Points | Estimated Time |
|
||
|
| -------- | ---------------- |
|
||
|
| 0 points | < 1 hour |
|
||
|
| 1 points | 1 hour - 0.5 days|
|
||
|
| 2 points | 0.5 - 1 days |
|
||
|
| 3 points | ~1 day |
|
||
|
| 5 points | 2 - 3 days |
|
||
|
| 8 points | ~1 week |
|
||
|
|
||
|
We should avoid 8 point stories by breaking them down into smaller stories as much as possible.
|