Scoping
- Wallet Router
- I've analysed the main components of the wallet router, see here:
Schedule
- I raised an axe to the crew meetings, swung hard and true. Toppled and prostrate they settled motionless. Tonight we revel in the light of their embers!
2024-05-13
Scoping
- Wallet Router
- I began work on reading and building context of the Route
status-go
logic. - This work is tricky to track, but I have begun making notes of the logic. I plan to continue to build out a description or documentation detailing the analysis.
- I began work on reading and building context of the Route
- Torrent dependencies in mobile build
- https://github.com/status-im/status-go/issues/5146
- Scope work for this issue requires more time, I've identified the imports and dependencies for implementing the backup distribution logic.
Schedule
- 10:30 – 11:30 : Discussion and sync with Sale about planning and scoping of Wallet Router work.
- Discussion giving context on the structure of the Router
- Discussed work done last week in : https://github.com/status-im/status-desktop/issues/14638
- We decided that we need to:
- spend time understanding the code
- determine what work can be parallelised
- 12:00 – 12:30 : Wallet Router Sync
- https://meet.google.com/amj-krdp-dta
- Attendees:
- Alisher
- Andrea
- Emil
- Ivan
- Jamie
- Sale
- Myself
- Notes
- Discussed what should be priorities
- Decided the following:
- Scope the Wallet Router to understand the logic
- Tests should be writen to validate any changes the Router code, but we do not build tests out without introducing changes.
- Tests can be written in the context of demonstrating / exploring how code works.
- Alisher was meant to present the product expectations, but we ran out of time.
- 14:30 – 15:00 : team update
- https://meet.google.com/vnx-agcb-nao
- A very sombre meeting, discussing the recent layoffs