Development is split in feature driven milestones. Each milestone's goal is to ship an identified set of features in a short (few weeks) time.
-High level scope of a milestone is agreed on by the whole team. Developers then create a set of atomic and detailed github issues. Based on those an estimated delivery date is defined. -Reasonable efforts are made to not modify the scope of a milestone once started.
-Issues are closed regularly to get good sense of progress. -If finished early, development proceed to next milestone.
-Workflow
-Once an issue assigned, a developer work on implementing and once ready pushes a PR. It's then its responsibility to make sure this PR gets merged quick. PRs are the only way to introduce new code in the codebase. -A trunk based development model is followed. A PR is reviewed with great care: ultimate goal is zero regression and master is considered production quality.
-Pull request content
-A pull request is linked to an issue. Sufficient information is provided so that the review process is simplified.
-How to link PR and issues:
--
-
- commit name: [#XXX] sldfjdsfj -
- PR title is the same as commit name -
- PR comment starts with
fixes #123for easier issue navigation
-
Definition of done
-To be considered ready for review, a pull request must (when relevant):
--
-
- not define TODOs -
- have a reasonable design (no hack policy) -
- be pixel perfect -
- have automated tests -
- have commented code -
- provide documentation -
- have been demoed -
Developers must go the extra mile to perform manual tests.
-Pull request lifecycle
-Once pushed a pull request will go through a review cycle. Whenever possible checks are automated, e.g.
--
-
- compilation / unit tests execution via CircleCI -
- code quality -
- patterns usage -
Once checks pass, the pull request must be reviewed. -Reviewers are assigned automatically, based on defined codeowners
-A reviewer might request changes. If agreement emerges an individual commit is created to simplify follow up reviews. -All commits are squashed into a single commit for final merge.
-Tooling
-Github tools are leveraged: issues, pull requests and milestones.
-A github project helps tracking overall progress. Kanban is roughly followed.
-Tags
-Tags are used to identify and track progress of issues and pull requests.
-Initial tags are first added by issue creator. Those can be completed by the whole team.
-Issues tags
--
-
- type: bug, enhancement, maintenance, question -
- priority: critical, high, medium, low -
- status: abandoned, duplicate, wontfix, on hold -
PR tags
--
-
- status: available, in progress, blocked by design, 3rd party, review needed, revision needed, accepted -