open-bounty/doc/development_workflow.md

75 lines
4.1 KiB
Markdown
Raw Normal View History

2018-02-15 08:27:36 +00:00
# Development process in Status Open Bounty
We have a continuously deployed version tracking the `develop` branch live at [test environment](https://openbounty.status.im:444). It uses the [Ropsten](https://ropsten.io/) Ethereum testnet. Any one is welcome to use it and contribute to Open Bounty.
Any help is greatly appreciated!
Currently we use two projects - `Pipeline For Issues` and `Pipeline For Pull Requests`, issues and pull requests in our repository are passing through all or several stages described below.
2018-02-19 12:28:16 +00:00
Whole team is responsible to keep the projects with accurate information.
**If issue or pull request marked with `Blocked` label, it means that it is blocked on some stage, reason of blocking have to be in comment.**
2018-02-15 08:27:36 +00:00
## Pipeline For Issues
2018-02-19 12:28:16 +00:00
Team is working only on issues that included in this project.
Issues can be added to this project by any core team member.
2018-02-15 08:27:36 +00:00
#### To define
This is backlog for all features/issues/enhancements which we want to include to development process.
All issues here should be marked with:
2018-02-19 14:14:48 +00:00
* **type** - `bug`, `tech-debt`,` enhancement` labels. Issues with `proposal` label should be converted to `bug`, `tech-debt`,` enhancement` before addidng to project.
* **priority** - `Prio: high`, `Prio: med`, `Prio: low` labels. On the board inside issues with same priority sorting from higher to lower priority is applied.
2018-02-15 08:27:36 +00:00
#### Defining
The column is intended for issues not completely clear or for features, that should be splitted to smaller issues in order to go ahead.
2018-02-19 12:28:16 +00:00
After defining all issues that are intended to develop should have size label
2018-02-19 14:14:48 +00:00
* `Size: XS` - 1-2 hours,
* `Size: S` - 2-4 hours,
* `Size: M` - 4-8 hours,
* `Size: L` - 8-20 hours,
* `Size: XL` - 20-40 hours,
* `Size: XXL` - 40-60 hours.
2018-02-15 08:27:36 +00:00
#### To design
2018-02-19 12:28:16 +00:00
It is used for issues that are already defined and require designing process.
2018-02-15 08:27:36 +00:00
#### Designing
It shows up that issues are currently in designing process.
#### To develop
It stores issues which are ready for development.
They are explained, clear, designed and **small enough to create one pull request per issue.**
2018-02-19 12:28:16 +00:00
#### In Bounty
The store with issues which are open bounties. When we put funds to issue and it shows up in [status open bounty](https://openbounty.status.im), we move issue here.
2018-02-15 08:27:36 +00:00
#### Developing
This is for issues that are currently developing, so pull requests assosiated with issues have to be placed in `Pipeline for Pull Request` project.
#### Done
It stores issues with merged to `master` pull requests.
## Pipeline For Pull Requests
#### Developing
Contains all open pull requests (hereinafter PRs) that already assosiated with issues.
2018-02-19 12:28:16 +00:00
#### Reviewing, waiting for contributor
2018-02-15 08:27:36 +00:00
It keeps all PRs from external contributors which should pass `Reviewing` stage.
#### Reviewing
The storage for all PRs that pass reviewing process.
Review process is discussed [here](https://github.com/status-im/open-bounty/issues/221)
2018-02-19 12:28:16 +00:00
The number of reviewers should be proportional to the complexity of the change and may vary from PR to PR.
Recommended:
* PR is trivial (from core contributor) - 1 approval from core contributor
* PR is normal (or from external contributor) - 2 or more approvals from core contributors
2018-02-15 08:27:36 +00:00
* PR need to be based on and opened against the `develop` branch.
* If a PR has undergone review and requires changes from author, move it back to `Contributor` column
#### To test
2018-02-19 12:28:16 +00:00
All PRs, that are already developed, reviewed, and haven't conflicts with `develop` branch, so ready to be tested.
In case if PR has conflict - it is moved to `Reviewing, waiting for contributor` for external contributors or to `Developing` for core contributors.
2018-02-15 08:27:36 +00:00
#### Testing
2018-02-19 12:28:16 +00:00
Contains all PRs that are currently should pass through testing process, which is described in `core_testing_workflow.md`.
2018-02-15 08:27:36 +00:00
After testing two scenarios possible:
2018-02-19 12:28:16 +00:00
* no issues assosiated with PR - `Tested: OK` label, merge to develop (using `Merge` button) to `Merged to develop`
2018-02-15 08:27:36 +00:00
* issues found - all of them are created as comments to current PR and PR is moved to `Developing`
2018-02-19 12:28:16 +00:00
#### Merged to develop
2018-02-15 08:27:36 +00:00
Keeps PRs that should be merged to `master` and deployed to [prod environment](https://openbounty.status.im/)
#### Done
Stores all merged and closed PRs.