@ -33,12 +33,14 @@ The Google Sheet will soon be replaced by a dashboard that extract data using Gi
|
||||
|
||||
### Terminology
|
||||
|
||||
| Name | Number of | Timeframe | Team Scope | Description |
|
||||
|----------------|-------------------------------------|--------------------------------------|-----------------------------------------|-----------------------------------------------------------------------------|
|
||||
| Priority Track | 3-5 | Set yearly | Whole Team | Focus set for the year, must be aligned with Logos Collective's priorities. |
|
||||
| Epic | 2-3 per _Priority Track_, total<=10 | Set yearly, delivered quarterly-ish | Several subteams | Identified deliverables for each _Priority Track_. |
|
||||
| Milestone | Some per Epic | Set quarterly-ish, delivered monthly | One subteam or external team (e.g. DST) | Steps to deliver an _Epic_. |
|
||||
| Task | Many per Milestone | Set monthly-ish, delivered weekly | One individual | Smallest chunk of work to be delivered. |
|
||||
| Name | Number of | Timeframe | Team Scope | Owner | Description |
|
||||
|----------------|-------------------------------------|--------------------------------------|-----------------------------------------|-------------|-----------------------------------------------------------------------------|
|
||||
| Priority Track | 3-5 | Set yearly | Whole Team | Waku Lead | Focus set for the year, must be aligned with Logos Collective's priorities. |
|
||||
| Epic | 2-3 per _Priority Track_, total<=10 | Set yearly, delivered quarterly-ish | Several subteams | Waku Lead | Identified deliverables for each _Priority Track_. |
|
||||
| Milestone | Some per Epic | Set quarterly-ish, delivered monthly | One subteam or external team (e.g. DST) | Team Member | Steps to deliver an _Epic_. |
|
||||
| Task | Many per Milestone | Set monthly-ish, delivered weekly | One individual | Team Member | Smallest chunk of work to be delivered. |
|
||||
|
||||
Owner = person responsible for the delivery of the milestone and related reporting.
|
||||
|
||||
### GitHub Usage
|
||||
|
||||
@ -46,7 +48,7 @@ For each:
|
||||
|
||||
- _Epic_, there is a GH issue under the https://github.com/waku-org/pm repo.
|
||||
- _Epic_, there is a label with format `E:<year>-<epic title>` created across all relevant https://github.com/waku-org/ repos.
|
||||
- _Milestone_, there is a GH issue under the relevant https://github.com/waku-org/ repo with related _Epic_ label and `milestone` label assigned.
|
||||
- _Milestone_, there is a GH issue under the relevant https://github.com/waku-org/ repo with related _Epic_ label and `milestone` label assigned. The GH issue is assigned to the _owner_ of the milestone.
|
||||
- _Task_, there is a GH issue and/or pull request under the relevant https://github.com/waku-org/ repo with related _Epic_ label.
|
||||
|
||||
Hence, correct _Epic_ label must be assigned to all GH issues/pull requests representing a _Milestone_ or _Task_.
|
||||
@ -69,7 +71,7 @@ Note: GitHub `milestone` functionality is **not** used as part of this process.
|
||||
|
||||
**Weekly**: Report progress on each **active** _Milestone_ per subteam.
|
||||
|
||||
Every Friday, all team members must add a comment to the `Milestone` GH issue they worked on the past week or planned to work on next week.
|
||||
Every Friday, all team members must add a comment to the `Milestone` GH issue they own and worked on the past week or planned to work on next week.
|
||||
|
||||
The comment must have the following MarkDown format:
|
||||
|
||||
|
||||